dear all,
hoa to change the cut off date in P6? in the schedule the cut off date falls every sunday, but i want it to be change every friday. thanks
dear all,
hoa to change the cut off date in P6? in the schedule the cut off date falls every sunday, but i want it to be change every friday. thanks
admin
admin preferences
General tab
Starting Dau of Week Chanhe this to Saturday
this will end the week on Friday
Select Enterprise-> Calendar from Primavera menu. Then select which one you need (Global, Resource or Project) to create. Click Add or modify existing and define it from there.
hi,
We can set it at Admin preferences->General->starting day of week.
Best Regards.