Program for Mosque

Forum Topic

Hi,   I am going to develope a program for Mosque ,any one who done project on mosque can help me .Just forward the program in P3/P6 format touse private message service Thanks guys .

Nov 1, 2011

Budgeted Labour Units

Forum Topic

Good day all can someone please explain why the budgeted labor units change when my plan is scheduled ? I am using P6.2 thanking you   France

Nov 1, 2011

Total Float

Forum Topic

  Please help me I am just wondering why how can an activity have a negative float of over -200 days when the overall total delay to the project is only -61 days?

Nov 1, 2011

UKOUG Next Month?

Forum Topic

Anyone going to the UK Oracle User Group Conference next month? http://bit.ly/uwc0Mw

Nov 1, 2011

What is a Reflection?

Forum Topic

HI Guys,Here's a good explanation on what a Reflection is in Primavera P6, complete with screen grabs. http://bit.ly/urr327I hope you find this useful.Emily

Nov 1, 2011

Project Controls: Producing a Horizontal Split P50 curve

Forum Topic

Hi,   I have searched but cannot find the answer to this question.   I have produced a programme using P6 vs.7, and dumped the Early vs Late data into excel, to produce early + late curves.   Now I would like to produce a P50 (50% float) curve, howev...

Nov 2, 2011

Grouping by Resource Name Problem

Forum Topic

Hi, I'm trying to produce a Gantt Chart report on MSP2003 which is grouped by the various resources. However, what I am finding is that if a task has several resources shown working on it, the task does not appear twice on the report (i.e. same task ...

Nov 2, 2011

Nonlabor units calculation

Forum Topic

To all PP master,I am QS in my present work and also assigned to do scheduling work,I am updating a master programme that originally created by others(Korean guy),the programme is cost loaded (budgeted cost base on BOQ), when I am trying to find out ...

Nov 2, 2011

Annually increased resource rates in P6R8

Forum Topic

An interesting problem has just arisen.We use fully resourced and costed programmes using P6R8 and I have just come across this.Our resource charge out rate changes every 1st April so I have added effective dates and correct resource charge out rates...

Nov 2, 2011

Annually increased resource rates in P6R8

Forum Topic

An interesting problem has just arisen.We use fully resourced and costed programmes using P6R8 and I have just come across this.Our resource charge out rate changes every 1st April so I have added effective dates and correct resource charge out rates...

Nov 2, 2011

Replicating an activity

Forum Topic

I have a project that I have imported from MSP.   I have 215 activites in which within this I have 7 sites. Is it possible to replicate each site within my activities for 6 years. (example Site 1-activities associated with each. It shows the schedule...

Nov 2, 2011

Gettign Earned Value Of Previous Dates.

Forum Topic

Hi All,I just came accross a demand from my project Manager.He asked me about the Earned value cost till the End of September,2011.The Program is only Cost Loaded (Using Expence Tab and there are not unit (Resources).I know that if you Reverse the da...

Nov 2, 2011

Financial Periods

Forum Topic

Hi All Primavera Users, I have created financial perioods for a Project "Project A" but when I created another project separately "project b" and tried to creat Financial periods for it,I have found that the Financial Periods for "Project A" are alre...

Nov 2, 2011

Estimation of Manufacturing Durations for Procurement Activities

Forum Topic

Hello good morning to my fellow planners. I am in a predicament of estimating manufacturing durations which I have to incorporate to my Master Schedule Most of them are Mechanical Equipments. Strippers, Vessels, Heat Exchangers, Tanks, Filters, In-Li...

Nov 3, 2011

P3 Progress Import - Actual Finish Dates

Forum Topic

Hi All I am importing progress data and am finding the Actual finish dates are not importing. The steps follwed are below. Export Activity ID, Activity Description, Actual Start, Actual Finish, Remaining Duration & Percent Complete using a .DBF file....

Nov 3, 2011

I want to add quantity(area in sqm or no.s)

Forum Topic

hi planners, how can i assign and define the area of a project..means the schedule for glazing of a building,the wbs prepared is based on floors- 1st floor,2nd floor etc.. i want to add and show the total area of glass using in each floor and no of d...

Nov 3, 2011

" Planned Dates"

Forum Topic

Please can soem one explaine to me what teh function of "Planned Dates" are in P6 and what benfit or use they are best used for ?

Nov 3, 2011

Deleting Calendars

Forum Topic

I have tried to delete global calendars but they will not delete due to being used on other projects.I have deleted all other projects and resource codes.They are not used any were else.I am thinking the problem is in the baselined project. How do i ...

Nov 3, 2011