I have a project that I have imported from MSP.

 

I have 215 activites in which within this I have 7 sites.

Is it possible to replicate each site within my activities for 6 years. (example Site 1-activities associated with each. It shows the schedule from 2012 to 2013 and I want it to show the same activities within that site for

If this is possible how would I go about doing this?

 

Thanks

Rhys

R
Rhys Parry 👤 Member for 14 years 8 months

Sorry Gary me and explaning sometimes don't go :)

 

What it is I have activities that are sub headed as individual sites with activities associated with them.

What I need to do is for each sub heading and their activities is replicate this for 6 years. So at the moment its from april 2012 to april 2013 for site A and Site B and Site C etc each having activities listed for them.

 

I was thinking of copying the individual sub headings within the WBS six times.

Does this seem like the correct solution.

Hope that helps

Thanks

G
Gary Whitehead 👤 Member for 17 years 2 months

Hi Rhys,

 

Apologies if I'm being dense, but I have absolutely no clue what you are trying to achieve. -Could you have anothe go at explaining it?

 

Cheers,

 

G

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts