Copying relationships for identical activities

Forum Topic

Hello everybody,My issue is I'm having a plan for a 51 residental buildings project, in a stage of construction there will be a lot of similar activities, so I create the activities in one building then I copy them to the other buildings , now I want...

Jul 5, 2011

P6 milestones against progress line

Forum Topic

On my milestones, my P6 progress line completely ignores progress on the milestones (0% or 100%) (ahead or behind) . Progress reporting on the Bars is fine, and the progress line is a good "zig-zag" drop-line. Is there a way of having the progress of...

Jul 5, 2011

Critical Path Quiz answers

Forum Topic

So here are the answers to the quiz, along with an explanation of how to compute critical path drag in a simple (all FS) network:Which activity or activities has/have the most total float, and how much? J has TF = 40Which activity or activities has/h...

Jul 5, 2011

Claim Digger

Forum Topic

Can anybody tell me how to use claim digger in P6. I am having the Icon in P6 window,but when i click it nothing is coming. Kindly help.

Jul 5, 2011

Remain Finish Date vs Remain Start Date.

Forum Topic

Hi everyone, I am using Primavera PM6 to manage the coming workload of our team. We have about 95 projects in progress with 4 to 9 activities in each project. My problem occurs when I open many projects at the same time, the remaining units of some t...

Jul 5, 2011

Just getting started with TILOS

Forum Topic

Im just delving into TILOS for the first time as a new planner. I emailed Tilos support for any reference materials or possibly any trainers in the vecinity of Salt Lake City Utah, but have not recieved any response.Im really  intersted in getting th...

Jul 5, 2011

Trouble Exporting MSProject 2007 files to Primavera Contractor

Forum Topic

I am having huge problems trying to export a project created in MS Project (by my owner) into Primavera's P4 Contractor.I need help so that I don't have to recreate the entire project from scratch. Anyone know a way or a file conversion utility to ac...

Jul 5, 2011

Working Dates Back in Project 2003

Forum Topic

This may be a basic question, but I want to design a plan that works back from a given delivery date. I've discovered I can enter predecessors with a minus number of days, but it doesn't appear to work the dates back consistently. Ideas?

Jul 6, 2011

Cost loading updates problems

Forum Topic

Regarding loading the schedule with cost what happens when updating that the actual cost is keeping changed for the nearly ended monthes i think becouse if there is an activity where its duration is is extended beyound its original duration so the pr...

Jul 6, 2011

Planning Package

Forum Topic

Hi friends Anybody  know about what planing package is? If yes,  please forward me documents.  Thanks, Sam

Jul 6, 2011

PLANNING SOFTWARE WIDELY USED IN CANADA

Forum Topic

I JUST WANT TO KNOW WHICH IS THE MOST WIDELY USED PLANNING SOFTWARE IN CANADA. I KNOW ITS PRIMAVERA IN GCC COUNTRIES ,IS IT SAME FOR CANADA AS WELL?

Jul 6, 2011

P3 Actual/Forecast Cost

Forum Topic

Dear planners;I need to make the forecast cost histogramme for the schedule, but I am not sure how?So, I have to make the update on the % progress cost (Actual Cost/Budgeted Cost Quantities) and P3 generate automaticaly the forecast Costs?OR I have t...

Jul 6, 2011

Driving calendars

Forum Topic

Everyone,   I currently have a 14 day (7 day calendar-no BH holidays) running through Christmas. It is the last path on the network, barring a finish milestone for 'planned completion'. which is its successor. This milestone has a 5 day claendar. As ...

Jul 6, 2011

MS project 2003 Duration and Finish does not reconcile

Forum Topic

I have a strange problem, I want change my clander from 8 hrs to 9 hrs. Before doing it on the project i experimentedCreated a new project put an activityName              Duration           Start              FinishTask 1                5days       ...

Jul 6, 2011

Steps in Acvitity Table

Forum Topic

Is there anyway to make the steps description appear in the activity table?  I'm tracking using one line items for different projects. 

Jul 6, 2011

Revision to Baseline with constraints

Forum Topic

Dear All, Due to delay in start client need two options, we already had contractual baseline. Option#1 End dates don’t change, duration as well as man-hours are fixed. Evaluate variance of manhours required to complete the job. Option#2 End dates cha...

Jul 7, 2011

Remove Progress and Links

Forum Topic

Hi,a) How to  remove complete progress instantly from the whole programme containing 1000  activties ? any tip  please share.b) How to remove links completely and instantly given to 1000  activties from the whole programme  ? Please tell me the steps...

Jul 7, 2011

Urgent Senior Project Planning Engineer Needed!!!!!!

Forum Topic

Dear All Senior Project Palanning Engineers, All Senior Planners that are looking to work for a remound name within the PetroChemical industry, please give me a call.             Kind           regards  MartinRoberts     (004969222213856) maroberts@a...

Jul 7, 2011