Search

Time Management Questionnaire

Forum Topic

I am currently undertaking research of time management practices in construction as part of an MSc in Construction Project Management. I would be grateful if anyone involved in the management of construction projects (even at pre-construction stage) ...

Jun 19, 2015

P6 8.1 and P6 8.3 from one Computer together ???

Forum Topic

Hi , Anybody come across this situation where you can use 8.1 client and 8.3 client together from one computer (ie: 2 instance at the same time) in an EPPM enviornment.  I am not able to open both together. I want to open 8.1 and 8.3 same time on sam...

Jun 19, 2015

Certification to Choose PMI / AACE

Forum Topic

Hi,I have been in Planning & Costing for 4 years. I do QS also. I would like to go for certification to work with global employers.I did a small study and compared different institutes and their courses (PMI / AACE / PRINCE2 / IPMA / AIPM).I filtered...

Jun 20, 2015

activity as a resource

Forum Topic

Hi!For example I have an activity of "preparing one serve soup" with resorces 0,5 lt of water, 3 tomatoes, a pinch of salt, 1 hour cook etc. Then I have another activity "preparing a dinner for 6 persons" I want to insert that "preparing soup" activi...

Jun 20, 2015

PMP Eligibility

Forum Topic

Hi ,I have total of 4 years expereince as Planner. I dont have Project Manager experience .Am I eligible to apply for PMP exam.Please adviseRegardsBadhru

Jun 21, 2015

METHOD STATEMENT FOR CONCRETE WORK

Forum Topic

Hello, I'm working on a simple plan for an office building. it's some how decided that project life time is double concrete work life time. so, what I'm looking for is productivity rates regarding to concrete work as well as Method Statement for Conc...

Jun 21, 2015

Seeking the way to define Progress Measuring Method in Primavera P6

Forum Topic

Hi to all, I have got new project & the project's scope is to rectify & renovate the Buildings. Here my Baseline schedule has been approved as per given Finish milestones by client & i loaded appropriate Manhours upon my experience because there is n...

Jun 21, 2015

Filter for tasks that should have started

Forum Topic

I need some assistance with a filter that will show task that should have started by the status date but still show now actual start or % progress

Jun 23, 2015

Activity time issues creating constraint issues

Forum Topic

I inherited a project schedule for a MILCON project in Southern California.  The project was subject to a long delay before actual construction began, so there are issues of time and money to tidy up.  In reviewing the older schedules that are part o...

Jun 23, 2015

Load Labor Units/ Manpower in an Updated Schedule

Forum Topic

Dear Friends,My Client is asking to load resources ( Manpower ) in the existing Primavera Schedule (P6)  which is already updated . I have never came across such situaion  and am not sure , technically can it happen. Can ayone shed some light on this...

Jun 25, 2015

Materials vs. Expenses

Forum Topic

How do you treat material costs? Given the distinction between expenses and material costs is depreciation, and there is either a Resource tab or an Expense tab (bottom Layout)[[wysiwyg_imageupload:2509:]]. how do you list your material costs-say bul...

Jun 25, 2015

Using Primavera outside of network

Forum Topic

Hi planners,Two question about using Primavera outside of the network. I have SQL 2012 express edition running on a server and when I login from inside of the network everything wors fine. But when I try to login from outside of the network, I get th...

Jun 26, 2015

Time Impact Analysis Schedule

Forum Topic

Hello,I was asked to prepare an example TIA - Time Impact Analysis Schedule in P6.To do this, I would first prepare a normal baseline schedule, and then, assign delays to certain activities and prepare a second, delayed schedule? And calculate a vari...

Jun 27, 2015