what does "I need a template for progress measurement for tracking engineering progress and also for tracking procurement progress" and ?How to use global change to change activity ID please?
have to do with
Loading resourse with global change ?
please create a new post do not piggyback on a diferent subject
option #1 as Raymund suggested is the global change will add the resource to all of the activities with the same code or wbs or any identifier
another option is at the activity level highlight the activitie that you want to add resource for and right click and select assign resources and select your resource.
yet another option is to assign a resource to one activity then export this information to excel and copy the resource information to the other actvities in the spreadsheet and import the activities back into P6 from excel. (make sure that calcuate costs from units is NOT checked)
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
@ BUSAYO ABIOYE
what does "I need a template for progress measurement for tracking engineering progress and also for tracking procurement progress" and ?How to use global change to change activity ID please?
have to do with
Loading resourse with global change ?
please create a new post do not piggyback on a diferent subject
I need a template for progress measurement for tracking engineering progress and also for tracking procurement progress
How to use global change to change activity ID please
option #1 as Raymund suggested is the global change will add the resource to all of the activities with the same code or wbs or any identifier
another option is at the activity level highlight the activitie that you want to add resource for and right click and select assign resources and select your resource.
yet another option is to assign a resource to one activity then export this information to excel and copy the resource information to the other actvities in the spreadsheet and import the activities back into P6 from excel. (make sure that calcuate costs from units is NOT checked)
Antonio,
Oprion 1...
Subject Area =Activity Resource Assignment. If Activity = (Select Activity Codes or WBS or any Identity) Then Resource ID Name = (Select Resource)
Option 2...
Organize your Activity Layout to group the Activities with the same Resources together. Use add resources under the Activity Detail.
Option 3...
Use the Excel Import through the SDK...
Regards,