Search

Filters. For the MASTERS only.

Forum Topic

Hi folksI am having some issues when creating a very selective filter. The information I want to display is very specific but to add salt to injury I can only use one filter and not a combination of them. As you know Reports in P6 only allow to creat...

Nov 12, 2012

FYI 64-bit Primavera Risk Analysis 8.7sp5

Forum Topic

Most of you may know this, but I just stumbled across it today: there is a 64-bit version of PRA that was issued in September (8.7sp5). No problem installing and it seems to be a little faster - need to test it on a plan with Risk Factors, to be sure...

Nov 12, 2012

Roll Up

Forum Topic

How can I get the Rolled up Values on the Summary Rows to sum up the Filtered values only. I have run a filter to show Material resourced Tasks only, but the Rolled Up costs show the Sum for all tasks (including the labour ones which are not showing)...

Nov 13, 2012

Delay Analysis

Forum Topic

Dear All, Currently I am working in a DG Sewerage project, our task is to calculate the delay for each shaft. My question is that how to link the delayed days with the total float of the BL . Also other than window  analysis is there any other method...

Nov 14, 2012

Adding Formulas to a Column

Forum Topic

I was wondering if it is possible to add a formula to user defined columns similar to how excel formulas work.For example (Column A x Column B) Thanks in advance

Nov 14, 2012

How to assign weights to Schedule ?

Forum Topic

I am exploring the way that how to assign weights to my schedule I am using cost & resource loaded schedule Duration Type = Fixed Duration & Units % complete type = Duration Duration % complete = 12.33% Schedule % Complete = 20.35% Performance % Comp...

Nov 15, 2012

Actual Finish vs Finish date (Should I use constraint date?)

Forum Topic

Fellow Planners, I am new to PV so you guys will have to humor me for a bit.Have a question about my finish date in the plan I have just created in PV. If a task gets completed earlier than "finish" date, when I put in the actual (and schedule), the ...

Nov 15, 2012

Critical Chain Project Management

Forum Topic

Does anybody uses Critical Chain Project Management .... which software supports this method of scheduling and tracking.

Nov 16, 2012

P6 to P3e - Is it possible?

Forum Topic

Hi guys,I was hoping someone would be able to assist on this small query of mine. I have been asked to put a programme together for a client of my employer. While reading through the contract, I seen a section that says the programme im putting toget...

May 28, 2012

Baseline Comments Received

Forum Topic

Baseline Comments. Some of the comments for a baseline are listed below. Appreciate your comments.1. Project Milestones. Is it compulsory to have successors to milestones.2. Restriction of maximum duration for activities to 20 days. Some long lead it...

May 28, 2012

Finish date is not same as Early finish or late finish

Forum Topic

Hi, I need urgent help. I am using p6v7.I never faced this problem. I have an activity with type WBS summary.In this we have Project start (15 sep-2011)and project finish(15-sep-2014). Early finish is 15-sep-2014.Late finish is 15-sep-2014.But the Fi...

May 28, 2012

Looking for P6

Forum Topic

I am looking for P6 files for model projects so please help me.Thanks

May 29, 2012

Daily Qtys - P6

Forum Topic

Morning All, Is it possible to add daily qtys into P6. Our engineers enter daily qtys into a spreadsheet and I would like to track it in P6. I am currently focused on tracking of crushing - I update the programme weekly and P6 spreads my qty evenly a...

May 29, 2012

Civil Infrastructure project help

Forum Topic

Hi Everybody!!!!!   I have been given a project of already built 30 villas and the project is planning of road, water supply, and electricity supply to those villas. I dont have any idea since previously i was involved with MEP building planning........

May 29, 2012

Powerproject and Lean/Last Planner System

Forum Topic

Hello All,Does anyone have experience or knowledge on how Asta Powerproject lends iteself to Lean Construction and Last Planner System?  Is anyone using the line of balance feature?Justin

May 29, 2012