Hi,
I need urgent help.
I am using p6v7.I never faced this problem.
I have an activity with type WBS summary.In this we have Project start (15 sep-2011)and project finish(15-sep-2014).
Early finish is 15-sep-2014.Late finish is 15-sep-2014.But the Finish col showing 11 sep 2014.
Can I adjust it or to show it equal to Early finish.
Urgent help please.
kp
Check if you have put must finish constraints
Check it your calender or resources, you will get ans.
Regards
Madan