Forum TopicHi PP AdminPlease can we have a BIM heading for threads on 3D and 4D topics.Best regardsMike Testro
Hi PP AdminPlease can we have a BIM heading for threads on 3D and 4D topics.Best regardsMike Testro
Dear Planners,Can any one provide me with the productivity rate for water pipeline installation in linear meter, bedding and backfilling?Regards,Moutaz
Hi,I've recently been asked to produce a consolidated schedule that consists of the contractors' schedules and the owner's schedule linked together.I've created the interface relationships between all schedules and everything works like a charm, exce...
I have just started on a project in Finland where we are cost loading the schedule.I am working with P6 Professional R8.2 Release 8.2.1 The problem we are having is that after loading all the costs, as soon as we try to update progress on an activity...
Hi All, It seems if I assign roles to a level of effort activity before I schedule it so the activity is of the correct duration, the distribution of the role will remain on the initial duration of the activity even after I schedule. Can anyone verif...
hi to all,i am searching a way to extract Activity Usage Spreadsheet from P6 to Excel for desired WBS.i have loaded cost on Engineering, Procurement & Construction Phases & my Performance Percentage Complete is 12.72%. here i want to see Planned & Ac...
Dear All,I have a problem related to an EOT Claim. Our project is a 10 Km long Highway & there are no sectional project completion dates as per contract.Currently, work is in progress but behind the schedule. Unfortunately, at the very end sections o...
A (non-planner) colleague wants to dosome classroom training on MS Project, and asked if I could recommend someone. can anyone help? Cheers, G
hi to all experts, after migrated form Primavera v 6.7 to 8.2 i am problem with Header & Footer.I am unable to edit & modify anything there. Do anyone know solution of this problem? , please share with me. thanks in advance.......
Hi all,I have two small issues with logical relationships, I hope you will get me out of this. The situation is as follows: I issue (Priliminary Clearance):The Project is a 80 Km Highway.I have two activities :A1) Clearing and Grubbing; andA2) Cons...
I was wondering if there is an easy way to create a filter for the longest path leading to a certain activity which is not actually on the longest path. I know it can be done by adding an artificial activity or lag which exceeds the current longest p...
Dear Planners,In my schedule, I have two resources assigned to specific activity, two of them I do not have any price and the other one has the price according to the BOQ. I tried to assign the priced one as primary resource but the program said that...
http://www.iter.org/org/team/adm/proc/expertDeadline for applications 16th Aug 2013
Dear All This is my first time time to work on EOT, but i have been guided through all your convesations in this forum and it was extremely helpful, i started and i reach this stage shown below and in P6 now i have these: 1- fragnet linked to the lat...
Dear Friends, Kindly answer my question. I have developed the baseline schedule, assigned and maintained the baseline and put a constraint to finish on 14thFebruary 2014. Then I have created the Financial period values starting from Wk-16 of 2013 t...
Dear Planet, How to produce a report where the total budgeted cost is distributed monthly in P6.1? I am only able to produce a report where the activity budgeted cost shows on the first month and not distributed for the whole period :( e.g. ...
Sometimes it’s the little things that can really differentiate a product from its competitors. One feature I really find invaluable and unique to Primavera P6 is the Progress Spotlight. Here's how it works http://ow.ly/nHUBh Emily
Good day Planners & The Like;I have a small problem, i am hoping its really that small.. well here it goes.I have made a Baseline Schedule Schedule out from our very own initial schedule. and so it goes.. after a few months of updating and revisions ...
HI. Need help. PM has rejected the below compensation events! Do i have a case if i take it to an adjudicator/court? Compensation Event #1Clause: 60.1The following are compensation events. (1) The Project Manager gives an instruction changing the Wor...
Hi all. Does anyone know how to create a filter wich only shows the activities that has changed (start or finish) in current plan compared to assigned baseline? cheers Haakon