Level of Effort Activities

Hi All,

It seems if I assign roles to a level of effort activity before I schedule it so the activity is of the correct duration, the distribution of the role will remain on the initial duration of the activity even after I schedule.

Can anyone verify this for me?  Are there other tricks with this? 

Thanks and Regards, Kylee.

R
Raymund de Laza 👤 Member for 16 years 6 months

Kylee,

Suggests to do the following:

1. In User Preferences ... Resource Analysis .. Review the "Interval for Time distributed resource calculations" if its matching your Time Scale.

2. After scheduling, Remove the Roles asssigned and re-assign.

 

Regards,