Hi All,
It seems if I assign roles to a level of effort activity before I schedule it so the activity is of the correct duration, the distribution of the role will remain on the initial duration of the activity even after I schedule.
Can anyone verify this for me? Are there other tricks with this?
Thanks and Regards, Kylee.
Kylee,
Suggests to do the following:
1. In User Preferences ... Resource Analysis .. Review the "Interval for Time distributed resource calculations" if its matching your Time Scale.
2. After scheduling, Remove the Roles asssigned and re-assign.
Regards,