Query on Primavera Software

Dear Friends,

Kindly answer my question.

 

  1. I have developed the baseline schedule, assigned and maintained the baseline and put a constraint to finish on 14thFebruary 2014.
  2. Then I have created the Financial period values starting from Wk-16 of 2013 to Wk-07 of 2014
  3. Then I have inputted the actual Man hours in the Schedule using Store  Period Performance.
  4. After Scheduling the project to current date,   the Finish date of the project is going to the week of May 2014 where as my Baseline Schedule finish Date is 14thFeb 14.
  5. Please explain why the Early Finish date is going beyond the Project Finish Date of 14thFebruary 2014 and how to fix the Early Finish date to 14thFebruary 2014 as shown in below Graph.
  6. Please explain how to find the No of Resources required to complete the remaining work.
  7. Also explain if we want to make any changes to the Schedule like adding Activities, Increasing the Budget etc., which should be appearing in Baseline schedule as well. Because when we tried to add a new activity by restoring the baseline and adding an activity in baseline schedule, it is not appearing updated schedule with actual.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts