P6.1 Reporting - Budgeted Monthly Cost

Dear Planet,

 

How to produce a report where the total budgeted cost is distributed monthly in P6.1? I am only able to produce a report where the activity budgeted cost shows on the first month and not distributed for the whole period :( 

 e.g.                           jan2013      feb2013    mar2013            

               activity101    $1,000        $1,000     $1,000

my report shows: 

                                   jan2013     feb2013   mar2013

                activity101     $3,000

 

Thank you ahead!

R
Raymund de Laza 👤 Member for 16 years 6 months

Adelfa,

1. Verify the Dates of your resources if it's the same date as your activity.

2. Verify the Calendar used for the Resource, it may be different from the Activity Calendar as well as the Default Calendar.

3. Press F9 to schedule.

 

Regards,

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts