Displaying a Prime Period Gantt Chart Bar in Primavera P6
Forum TopicHere's a useful step by step guide on how to display a Prime Period Gantt Chart Bar in Primavera P6 http://ow.ly/rrc73023e1k
Here's a useful step by step guide on how to display a Prime Period Gantt Chart Bar in Primavera P6 http://ow.ly/rrc73023e1k
I have just installed the latest version of P6 Professiona Project Manager 16.1. Trying to do a practice export unsing the UN/CEFACT XML - radio button on the export wizard. I it won't export to my desktop window. I get an Application Exception: Type...
hi,when we export P6 file to MSP file it is not converting all data into MSP rightly , like Lag is not getting in MSP, Actual finish dates are not getting correct and % column also nopt getting right in MSP converted file from P6 can you explain the ...
L.S.I was hoping that you could help me with my Thesis!The subject of my thesis concerns Project Management Tools. The why, how and what behind it.Please fill in this 4 minute survey and help me graduate!!https://nl.surveymonkey.com/r/AdH-GDKR37N Tha...
Here's some great tips on how to handle out-of-sequence progressing in Primavera P6 http://ow.ly/ZfYF3027A1r
Dear AllI am getting an error from today while try to make a pdf from p6 8.4 as follow, please help to resolve this issue%%[ ProductName: Distiller ]%%%%[ Error: typecheck; OffendingCommand: ifelse ]%% Stack:{F}{--dup-- /Encoding --get-- --dup-- Stan...
Hi;Can anyone help with the following.My previous actual units changes everytime I update (Schedule Project). I'm Sure I Untick the mark next to "Recalculate Actual Units & Cost when duration % complete changes" at project level.note:- the actual cha...
Two articles on LinkedIn have generated a lot of great discussion in the Comments. The articles, written by me, are titled “Seventeen Years Later, Doesn’t Critical Path Drag Belong in the Sixth Edition of the PMBOK® Guide” and “Drag Is NOT the Most I...
Hi Everybody :)I am using Primavera P6 rel 8.4 to exeperince some scinarios in constuction projectsafter partial planning and trying to enter Actual units for cost/time controlI found the the resultant Actual cost very high?see the screenshot [[wysiw...
Hi, A user of our P6 database has requested the ability to use reflections however their current planner security profile does not let them do so. Please can anyone let me know the Global and Project Security Privileges needed to allow them to use re...
.
I've setup P6 EPPM 16r1 and I can login using both web access and the client. However, I'm unable to add users. When I select the Administrator link and User Access, I get a blank screen with no options. Everything else seems to be working fine. I've...
Good day all.For many years now I have tried to get a very specific answer to a resource and cost related issue with Primavera from all kinds of industry experts, training experts and Oracle themselves, all to no avail.To pain the picture, what would...
Hi guys Just want to share a sample construction dashboard, it was developped using Microsoft PowerBI https://app.powerbi.com/view?r=eyJrIjoiOThhMGRjNDYtZGIzZS00NGU2LWE5MTQtMmViMThlNjcxYTdiIiwidCI6ImI2ZWM3ZGYwLTc1ZGEtNDc2Ni04MGI0LWNlYzM1MzZlNGYzYSIsI...
what is the difference in Variation and change order?Can someone please clarify?
Good day all you Planning Professionals! I beseech you for your wisdom. A lowly CM seeks a simple(well,,not for me) answer to a simple question. I am using MS Project 2013. I want to create a dependency from finish to start but i'm not sure how to do...
Hi P6 Experts,I need your help. We have a Master Schedule that consist of the 3 Construction Areas. I have 3 different P6 schedulers responsible to update each areas and send me the update. They are allowed to change the activity relationships, add ...
Hi,I'm doing tracking of activities % for my project. I keep getting the total float for the activity which i updated negative eventhough the % is not zero and it started ahead of the scheduled date. Could anyone help me? Been cracking my head on thi...
What quantities do I need to consider when I am preparing a Baseline Programme "Clause 14 Programme" if there are differences between BOQ and contract drawings on a Remeasured Contract? Thanks
I'm using P6 for scheduling a project. I have 3 activities that don't seem to level correctly. See below for example.All are Task dependent activitiesSame resource assigned to all activitiesCalendar is set to 8 hours/day work scheduleI have 3 tasks...