hi,
when we export P6 file to MSP file it is not converting all data into MSP rightly , like Lag is not getting in MSP, Actual finish dates are not getting correct and % column also nopt getting right in MSP converted file from P6 can you explain the procedure of export in more details
have you tired exporting it to an xml file ?
The issue is that it does not work. For example MSP and P6 calculate lags differently. To do the job properly you need to buy software to do the conversion. Collabro's Legare for example.