What quantities do I need to consider on Baseline Programme preparation for submission/approval for Remeasured contract?

J
JERICO AWAT 👤 Member for 19 years 1 month

What quantities do I need to consider when I am preparing a Baseline Programme "Clause 14 Programme" if there are differences between BOQ and contract drawings on a Remeasured Contract? Thanks

M
Mike Testro 👤 Member for 20 years 5 months

Hi Jerico

You build to the drawings not the BOQ - so the programme should be based on the drawings.

Best regards

Mike Testro

U
Umer Mehmood 👤 Member for 10 years 4 months

It depends upon the scope of work and associated time line , if there is a commitment on contract drawings with given timeline , i think than contract drawing should be used.

Eg concrete as per drawing is 1000 cum while in BOQ it is only 750 , than preparing schedule on 750 will not reflect actual condition , If the drawings did not change than schedule will not be valid since qty exceeds

Thus the claim for additional time due to mistake in BOQ cant be claimed.

Usually in re-measured contract BOQ is not accurate , people continue to refer to drawings for changes 

 

Regards

 

Umer Mehmood

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts