What quantities do I need to consider when I am preparing a Baseline Programme "Clause 14 Programme" if there are differences between BOQ and contract drawings on a Remeasured Contract? Thanks
What quantities do I need to consider on Baseline Programme preparation for submission/approval for Remeasured contract?
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Jerico
You build to the drawings not the BOQ - so the programme should be based on the drawings.
Best regards
Mike Testro
It depends upon the scope of work and associated time line , if there is a commitment on contract drawings with given timeline , i think than contract drawing should be used.
Eg concrete as per drawing is 1000 cum while in BOQ it is only 750 , than preparing schedule on 750 will not reflect actual condition , If the drawings did not change than schedule will not be valid since qty exceeds
Thus the claim for additional time due to mistake in BOQ cant be claimed.
Usually in re-measured contract BOQ is not accurate , people continue to refer to drawings for changes
Regards
Umer Mehmood