Hi Everybody :)
I am using Primavera P6 rel 8.4 to exeperince some scinarios in constuction projects
after partial planning and trying to enter Actual units for cost/time control
I found the the resultant Actual cost very high?
see the screenshot
[[wysiwyg_imageupload:4349:]]
what could be the problem?
thank you for sharing your knowledge :)
wrong forum
go to project higlight your project go to the calculations tab
under resource assignments make sure that subtract actual from at completion is checked NOT ADD actual to remaining