Cost loading issue

Forum Topic

Hai Everyone,  Can Anyone Please help me out,  When i am trying to Import the cost loaded File in P6 , about 20% of the activiites are showing zero value even though i assigned value , rest of activities are all Ok .. can any one tell me why 

Jun 25, 2016

08 MANAGING PROJECT COST ESTIMATING & BUDGETING

Forum Topic

http://www.mediafire.com/download/h32cl7rbl5ti1pl/GPCCAR_08_as_of_2016-01-05.pdfThis module references are representative of typical USA federal government contracting practices but misses the much wider universe of USA state/municipal governments an...

Jun 25, 2016

Cannot find Actual This Period Cost column...?

Forum Topic

I want to match the layout of a schedule pdf has a column called "Actual This Period Cost".  I cannot find a column with that name.  I can pull up period Material Cost, etc but not the "Actual this period cost".  I want to match the pdf layout of an ...

Jun 28, 2016

How can I import MS Project 2013 to Primavera P6 16.1

Forum Topic

I am wanting to import a Microsoft Project Professional schedule over to Primavera but keep getting ''Process completed with errors.  See log file for details'' as a result. I am following the steps on the Youtube video here: https://www.youtube.com/...

Jun 29, 2016

Resume Built using Primavera Project Management P6

Forum Topic

Hi, I have prepared my resume using Oracle Primavera Project Management P6 which resulted in amazing experience. You can see the below link to access. Comments are welcome. https://www.linkedin.com/pulse/resume-built-using-oracle-primavera-p6-mujahid...

Jun 29, 2016

Acumen Fuse - Fusing WBS Filters

Forum Topic

Hi, Can anyone tell me how I would fuse a WBS thread?  I need to prove schedule quality for various aspects of my programme.  I am building a plant with 4 stand alone facilities and whilst it is good to show the overall schedule quality, critical act...

Jul 2, 2016

P6 EPPM to MSP

Forum Topic

Hallo All, May be you had already discussed this topic but I have recently joined PP and I need some expert advise about below query:We installed P6 EPPM (16.1) in our organization very recently. But since we mostly do small to mid projects and many ...

Jul 3, 2016

P6 - Resource Icon Variations

Forum Topic

Hello All, Working in P6 R8.3.5 and have noticed that I have a couple of variations on several of the resource icons. I have a labour resources that are apearing with a small star and non labour resources apearing with a white arrow overlay. Have gon...

Jul 4, 2016

Drivin predecessor/successor info in SQL DB

Forum Topic

Hi,Do anyone know, if information of driving predecesor/successor is available in the SQL DB.I am trying to do a report directly from the DB, but have not been able to locate the information if a relationship is driving.Please let me know if this is ...

Jul 4, 2016

Drivin predecessor/successor info in SQL DB

Forum Topic

Hi,Do anyone know, if information of driving predecesor/successor is available in the SQL DB.I am trying to do a report directly from the DB, but have not been able to locate the information if a relationship is driving.Please let me know if this is ...

Jul 4, 2016

Resource Curves issues

Forum Topic

When using a resouce curves to assign cost to the very end of an eactivtiy, the cost is not always in the correct month if end of the activity is in the first few days of the month,I assume that when creating a curve it doesnt actually have it as 100...

Jul 5, 2016

Show Hammock allocation in a column at task level?

Forum Topic

Hello,I have a project on Asta that uses hammock tasks to summarise packages of work. I've been searching for a way to add a column that shows what hammock a task is assigned to; does anybody know if this is possible?Any feedback would be greatly app...

Jul 7, 2016

Primaver P6 version 8.4 - Unactualizing Dates

Forum Topic

Hello,I am using P6 Version 8.4.  I've been noticing that my finish dates are unactualizing (the 100% stays but the finish date pushes out to the current data date) - just wondering if anyone else has had this problem and how they fixed it.  I've had...

Jul 7, 2016

Remaining Late Units before Data Date

Forum Topic

Hi everyone,I was updating the progress. Wanted to extract actual & remaining labour units from primavera P6 R8.2in order to create Actual & Forecast curves.I checked the forums, tried some options like:- Negative Float - I have none- Constraints - T...

Jul 8, 2016