Hi,
On conversion of P6 programme in MSP, there are more crtitical activities in msp programme in addition to the critical activities of P6 programme. Has anyone came across such situation?
Hi,
On conversion of P6 programme in MSP, there are more crtitical activities in msp programme in addition to the critical activities of P6 programme. Has anyone came across such situation?
Thank you so much Tom.
Thank you so much Tom.
What version of P6?
What version of MSP?
What type of transfer file? (mpx?, xml?)
Even after a perfect translation of the activity definitions, logic, calendars, and constraints - the number of tasks and the definition of "Critical" can be different in the two tools just based on your update status and calculation options.
First, "Longest Path" does not exist in MSP, so all "critical" flags are set based on Total Slack alone.
Second, WBS levels in P6 may be converted to summary tasks in MSP. If you are simply counting "critical" tasks, the new summary tasks may be included in your count.
Third, the schedule might be calculated differently:
Finally, even if calculated dates are identical, Total Slack/Float might be calculated differently: