I have a project on Asta that uses hammock tasks to summarise packages of work. I've been searching for a way to add a column that shows what hammock a task is assigned to; does anybody know if this is possible?
Any feedback would be greatly appreciated.
Thanks,
Rich
Hi Richard,
You can use the parent name colun which is found under the identification category.
Hope this helps :)
Hi Richard.
Just change the code of the new task.
Best regards
Mike T.
Thanks Mike, the only problem I have with that method is if I copy a task and it copies the code to the new task even though it's not allocated to the hammock of the original task. I wasn't sure if there was any other way of showing that the new task is not allocated to a hammock without doing it manually.
Hi Richard
Assign a code to each task and then assign the same code to the hammock.
Best regards
Mike T.