P6 EPPM to MSP

Hallo All, May be you had already discussed this topic but I have recently joined PP and I need some expert advise about below query:

We installed P6 EPPM (16.1) in our organization very recently. But since we mostly do small to mid projects and many of our clients needs schedules in MSP, we used to convert P6 to MSP when we had stand alone P6 8.1 version. But after 16.1 is installed, we are facign issue of not been able to export projects from P6 to MPP or xml. Can anyone suggest a work around? 

Thank You so much in advance. 

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts