Search

P6 database configuration

Forum Topic

Hi all, I have problem with my P6. I'm using P6.7. I cant excess primavera n need to configure the database connection. I tried all the username and password as suggested by members in the forum but none of them works. Can anyone help me regarding th...

Sep 16, 2010

Project Planning and Control

Forum Topic

hi to all, Is there anyone who had a Project planning and control (using P6) manual by paul harris. kindly inform me where i can get it for free.   thank you

Sep 16, 2010

How to Change Cutt off dates (weekly base)

Forum Topic

dear all,hoa to change the cut off date in P6? in the schedule the cut off date falls every sunday, but i want it to be change every friday. thanks

Sep 16, 2010

Import via excel into the WBS table

Forum Topic

Using P 6.2.1, I want to import into the WBS table via excel (to save typing). Anyone know how to do this?  Thanks, Mark

Sep 16, 2010

Combining 3 seperate projects into 1

Forum Topic

Help. I want to to take 3 separate projects and combine into one. Each one will be used for either Primary, Secondary or Tertiary. How can you do this combine in P6? Thanks, James B.

Sep 16, 2010

Multi-Resources in Report

Forum Topic

If I run a report to view all my project resource budgeted hours everything shows up. In another report I created to show budgeted hours, earned hours, at completion, and scheduled % complete and then set my filter to show all resources I need, not a...

Sep 16, 2010

Bad weather calendar

Forum Topic

Hi eveyone its me again! Im still working on our Master Schedule and this time they required me to put up a Bar Weather Calendar, the specs include MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS, the thing is how will I apply it on the schedule?...

Sep 17, 2010

Default Curve To All Resources

Forum Topic

Can we assign / change the default curve on all the resources that are assigned on activities?Like i want to assign a TRAPEZOIDAL curve to all the resources on all the activities.

Sep 17, 2010

Define fields in P6.

Forum Topic

Hi Guys, Trust you are doing good. I am trying to define a field in P6 and make P6 calculate its value in the future like we can in excel. I know how to define a user field and classify it as a number/start date/integer etc., but is it possible to pu...

Sep 17, 2010

schedule percentage complete

Forum Topic

how can i create a graph of schedule percentage complete, schedule plan & actual together. I have not added any resources yet nor costs in the project. but say, I have information that out of 100 activities 40 activities have started and out of this ...

Sep 17, 2010

Microsoft Project

Forum Topic

Hi guys!can anybody help me where can i download a microsoft project software? i tried some torrent sites but i always got the microsoft office software..any torrent/link/website please? thanks a lot..

Sep 18, 2010

Level-3 Schedule

Forum Topic

Hi -Experts, We got (awarded) one project that is Chemical Plant Project size is small .project duration is 13 Months, Project manager asking me to prepare a L3 schedule while i do not have enough information to do so, information like Procurement , ...

Sep 19, 2010

Other Program Change upon Global change

Forum Topic

 Dear experts. What is the possible mistake done upon having a global change  with a program "C" that other program "A" and "B" in other EPS changed also as what in program "C"?. Global change is Rebaseline. Program "C" is a copy of program "B" but d...

Sep 19, 2010

Productivity Reference in P6

Forum Topic

I hope I am not putting myself in trouble. I have transferred a productivity book to P6. It's from the KSA Chamber of Commerce dated 2007. I wanna share it but I am thinking I might be putting myself into trouble. It's almost 98% done but I don't hav...

Sep 19, 2010

P6 Export of estimated weight and user cost in WBS level

Forum Topic

Dear all,In WBS page we have the Estimated Weight and User Cost for each WBS i try to change these values using any tools but i failed also try to export them in excel but also failed.i try to add different weights like Cost weight, Equipment weight,...

Sep 20, 2010

How to keep activity dates after levelling resource

Forum Topic

Hi everyoneI have a problem with preserving dates after leveling. For example i have totally seven activity; six of them linked FS  and other one is not have any successor or predecessor. Thats why two activity start with project start. After applyin...

Sep 20, 2010

Lost resources & Cost during export/import

Forum Topic

Hello Guy! I have problem regarding my schedule loaded with resources & cost, everytime I export and import the project I lost the budgeted cost that I have loaded in each activity.. Any solution to my problem...

Sep 20, 2010