Showing Near-critical Activities in Primavera P6
Forum TopicHere's some quick tips on how to show near critical activities in Primavera P6 http://ow.ly/z50rY
Here's some quick tips on how to show near critical activities in Primavera P6 http://ow.ly/z50rY
Hi ,Can you please advise me the best way for integrateing GIS data into P6 schedule, or visulaise the schedule on the poject Map based on GIS data? Thanks
HI GUYS CAN SOMEBODY HELP ME WITH SPI AND CPI CALCULATIONS.Actually I wanted to know the linitations of SPI & CPI.what is the acceptable limit of SPI and CPI. Thanks,
I am trying to do up a resource calendar availability roster using SQL.I can extract where the resource is on several projects, but they are putting their recreational days off onto their calendar. There is one calendar per resource, and I am unable ...
Please can anyone help me in telling me that i have windows 7 32 bits. Can i install P6 V8.2 in windows 7 32 bits?
Hi, I have been working in a Project with duration of 9months, supposed to complete by Sep'13. Due to various alterations in the Finishing Schedule and Nomination of new works, the project has been dragged till date, with every day addition of new wo...
Hi Hopefully someone will be able to help. I wish to have multiple "text only" fields in the columns. Asta bydefinition has 5 user text fields. I need 4 or 5 more. I have followed the asta help tool and done the following 1 entered the user fiel...
Hey guys I am working on MS Project 2010 I'm setting up a large scale project and wonder if I could assign resources i.e. discipline supervisors to the various summary tasks in my schedule and the units spread out at a granular level yet. For example...
The rather useful Microsoft Project 2010 Project Summary Task explained http://ow.ly/zjiwW
I just finished a Red Vector course on QA/QC. Does anyone follow/utilize Quality Assurance Programs? Has anyone seen/use any QA/QC checklists, guides, procedures to ensure 'conformance to requirements' as relates to Project Management? My industry...
Hello,I am creating a new schedule and want to understand best practices by experts here.How are you managing engineering or document approvals in your schedule?Submission/Approval - as a single activity?Submission linked to approvals - as separate a...
Dear All,For the construction of a sewerage network how can we arrange a sheet piling schedule inorder to cover a manhole seriesranging from 5m to 14m depth. Productivity will be varying depends on depth also re-using of sheet piles are also a matter...
http://youtu.be/AWLbNw2KuMA This video tutorial shows how to transfer an existing project schedule created in Primavera P6 to a Time Location Diagram in TILOS. The TILOS Exchange Software is used. 20min to invest for a better understanding of the con...
Hi All,Please can any one help me out on this issue; I have just built a new plan and fixed all links (Relationships) with the lags. Then I scheduled the plan and the contract start date changed to the scheduled date, which then changes the whole dat...
Dear All, I have re-baselined a percentage complete (earned Man-hour value / budgeted Manhour value) v/s. Time S - Curve at 75% project completion.Subsequently I have been asked to determine Retrospectively , what was the earned value % when the pro...
Good morning everybody!Just a quick question probably for some of you:Is there any free software I can use to create fast and clear small programme with the pourpouse of rapresentation/comparison of programme?I try to explain it better:Sometimes I wo...
Hello, I represent ISS Art, LLC, a software development compeny. We’re going to organize a free webinar, and we need to define the topic that would be the most interesting. Currently we have the following topics in mind:1. Time tracking systems2. ...
Hi all,I'm trying to make the actual labor units equal to the earned value labor units. I would like to do this either by global change or through export/import (excel).I know I can do it manually, but that costs a lot of time. And I do understand, t...
What exactly is an out-of-sequence activity and why do I care? Learn more http://ow.ly/zx2NU
Hello, new guy here. I've seen several different schedules, by several different schedulers, that have their LOEs with the SS and FF relationships as predecessors only. Reading up on all the material I can find nearly everyone says, from P6 docume...