Hey guys I am working on MS Project 2010
I'm setting up a large scale project and wonder if I could assign resources i.e. discipline supervisors to the various summary tasks in my schedule and the units spread out at a granular level yet.
For example if I have set of tasks running in sequence with overall duration of 17d on 8hrs/d and work equals 136hrs
A = 5d
B= 6d
C = 6d
Is there a way to assign this supervisor resource so that the work units (man-hours) could be spread out equally among these tasks
I've tried several methods and still can't find a solution so I thought I'd post it. I simplified a test project to test different ideas and still can't work it.