Microsoft Project Conference 2014?
Forum TopicWho's planning to go to the Microsoft Project Conference 2014? http://ow.ly/rGTF2
Who's planning to go to the Microsoft Project Conference 2014? http://ow.ly/rGTF2
Hi , I recently updated an actvity as completed , and accordingly have remaining duration and remaining units as zero.Howvever in resource tab , for the same activity i have remaining uint/ hr as 1 eventhough remining units are zero.I was expecting ...
Hello,Are there any standards in construction companies of reporting primavera schedules?As a planning engineer how should he report according to international standards? any format or anything ?
Dear Engineers,My project has not commenced contractually as the Advanced Payment and LC have not been received and opened, however the owner asked us to start constructing the site which was actually started and nearly completed, now I am going to e...
A new White Paper with a succinct definition of the project controls function can be downloaded from: http://www.mosaicprojects.com.au/WhitePapers/WP1093_Project_Controls.pdfAny thoughts or comments welcome (but please note, this is a functional defi...
Dear All/Mike,In version 12, I have seen some curved links. Suppose if I give FS link, it should be vertical but in version 12 , sometimes it shows curved one not vertical. How can I activate Automatic Curve Settings of all links in Asta version 12? ...
Hi guys,Anybody here has experience of Tunnel Construction? What is the best percent complete type to use? How about the duration type as well as activity type?Any input is highly appreciated. Thank you.
Hi, Can planners kindly shared your experience on how you have successfully mitigate a project, with some reference cases. Br TT
Dear All, I have few doubts which i want to clear., please help me to learn the real basics behind these.Let me explain you why I got all the doubts … I made a cost loaded schedule and assigned baseline to the project and made a schedule percentage c...
[[wysiwyg_imageupload:1890:]]Hi SirI have a question about P6. I am preparing one porgramme but i have an old copy of other project. it is simile like this .So i attach the image.This programme is not a progress programme , it is only for initial sub...
Dear AllOurs is an item rate contract .Any item which are not mentioned in BOQ is a variation item with a fixed mark up margin.Now Client provided us electricity @ one point.Charges & maintanance are born by us.Now Client insist us to share the elect...
hii,i have a problem in primavera, How to seperated the bill of quantity units and generate the monthly report.ex :Earth work in Filling units -3800265 cum and rate 233 rs per cum for two yearsHow to divide the the units (Material (Earth) + labour(La...
Here are 5 things your Project Stakeholders want to hear you say http://ow.ly/rOwZL
Dear All,I would like to know that is it correct to submit an EOT even before the conclusion of an Employer Risk Event? In the project I am working on there has been a delay in the delivery of one of the Client supplied material. The installation of ...
Hi, I have received a project schedule, it seems to have a baseline, but when I go to the Manage baselines, there is no baseline related to this schedule.I tried creating a copy of the current project as the baseline (which would then be the only act...
As a project controller, planner, laims planner or delay analyst, which one will be more useful PMP or RMP ?
Iam Rahman from India. Graduated Mechanical engineer passed out in 2012 currently working as Planning and billing engineer trainee in a small firm for an expansion of Petrochemical plant. I have lot of doubts kindly please help me because am a freshe...
Primavera Training Classes Dubai, Abu Dhabi,sharjah and UAE - Faastrackk Primavera is and extremely Powerful Enterprise Project Management Solution for Project Planning, Tracking, Controlling, and Reporting to ensure successful delivery of complex pr...
Morning all, Can you help at all? I've been sent a project in P6 which I've imported and taken a baseline so that future versions can be measured. however the dates on that baseline are differnt from the project it was taken from. one has altered by...