Hi ,
I recently updated an actvity as completed , and accordingly have remaining duration and remaining units as zero.
Howvever in resource tab , for the same activity i have remaining uint/ hr as 1 eventhough remining units are zero.
I was expecting even remining unit/ time as zero since there is no more to spend on that actvitiy.
Hope some one can throw some light on this.
Thanks in advance,
Vinod Raturi