Resources leveling tool
Forum TopicDear all,Does anyone know a tool for leveling schedules that is more efficient than P6 ?Thanks
Dear all,Does anyone know a tool for leveling schedules that is more efficient than P6 ?Thanks
Dear All, I am having a strange problem, which I never face while using Rel-6.0,6.2,7.0, and that is while deleting/or copying a program, It states a error code-TINAT-2680-D, or mentioning there is not enough space in database. Please any one advis...
Dear all,I am playing with diagrams and table reports now and have a couple of questions. Just checking, that that I understand the things correctly and not missing something:Both diagrams and table reports are possible to save as a template for futu...
I have to develop a schedule in P6 8.3 that integrates separate schedules from different Subcontractors. Since some of the financial information from the Subcontractors’ schedules is confidential, I intend to create separate schedules under a single...
Dear Primavera Experts, My question is, How can I display the total float on the Project summary level?The project completion milestone delayed 68 days (TF=-68), But on the project level it shown (TF=0), how can I display on this level the same TF wh...
I'm trying to install Primavera P6 V8.3 standalone on a notebook with windows 8 but I can't make it work. I would like to install it with SQL, if possible. Does anyone have some tutorial or some tips? Thanks!
Here's a blog that explains variance reporting in Primavera P6 Professional http://ow.ly/qJB0m I hope you find it useful. Emily
Is there a way to show the cost account name along with the cost account ID when it is used in the resource section of an activity? One does not have the option of adding the name column.Thank you.
Hi everyone,I have an activity that was completed earlier than planned (nov 1st instead of nov 8)Meanwhile its successor remaining early start date remains on november 11th. (the data date is nov 1st)Is there a way to advance the rem. early start to ...
Hi All, I want to filter activities between two dates in future, lets say 1June2014 and 30June2014. I am on P6.1, I would want to filter all activities including the ones having early dates inbetween and the ones progressing, i.e. started in April or...
Is there any way to know the login history on Primavera P6 8.2 running on Oracle database?
Today i logged in the system with the admin user i found that all the preference have been changed and all the user layouts and filters are deleted and some users are deleted too. anyone have an idea how this happen?
hi to all, here i am wondering a way to update my Recovery Schedule and Baseline @ one time by export & import method. I have same activity, duration, relationship in both schedule but my priority is to update my recovery schedule first & in the same...
Hello Friends,In Asta, I am actually looking for hiding the column option but still no success.Mike and other experts users can tell me about that.Thanks,
Hello everyone, Has anyone taken the CIOB time management assessment exam? I am curious to know the format of the exam and the difficulty.Example questions would be very helpful. Thanks,Vas
Hello, Please does anyone have a template or procedure on how to perform a schedule risk assessment wihout Monte Carlo and other specialty tools.Rgds
'PMO - Practice Makes Permanent' - Get good and stay good http://ow.ly/qOHKt
I've switched a lot of check-boxes today trying to find out why I get a calculated EV equal to PV everywhere and now doesn't even compute the Budgeted column in the Summary tag of the activity detail. Have you encountered this situation? Can you gues...
Hi colleagues,I have some clarifications here, I have successfully installed the P6 EPPM on a server with the following components:1.) MS SQL Server 2005 Express2.) Installed the P6 EPPM database3.) Configured the P6 EPPM via Configuration Wizard4.)...
Are there any options that be set to Check Out a project from Release 8.3 so that it cane be opened by Release 8.1. Best regardsHarold