Hi All,
I want to filter activities between two dates in future, lets say 1June2014 and 30June2014. I am on P6.1, I would want to filter all activities including the ones having early dates inbetween and the ones progressing, i.e. started in April or May and progressing in June of 2014.
Thanks,
Pranab
Hi Jean,
Thank you for your reply!
It has to be
Early Start < 30June2014
Early Finish > 1Jun2014
Thanks a lot!
Pranab
Create a filter "All of the following" with early start less than or equals June 30 2014 and late finish greater than or equals June 1st 2014