Search

Reference for previous forecasts???

Forum Topic

Hello All, Would really appreciate a prompt response for this one...   While it is expected of a Project Manager to change his At completion units to forecast and then baseline it keeping the budgeted units as they were, my understanding is that the ...

Sep 18, 2012

Project Control Method Statement

Forum Topic

Fellows, Anyone can share their narrative statement on how the project control method statement develops in general. The process comprise of 3 major disciplines which is ENGINEERING, PROCUREMENT AND CONSTRUCTION.Thank you, appriaciate your response.

Sep 18, 2012

Actual Date of an activity

Forum Topic

Hello friends, I have assigned the Actual Date of an activity as 10-july-2012 Now i came to know the activity has not yet started. When i click the Actual Check box in status. The report comes as, "Cannot set status to Not Started if activity has act...

Sep 18, 2012

Level of Effort % Complete

Forum Topic

Hey Guys, I have a question about Level of Effort. I am using P6 v8.2. I am trying to get the level of effort to update the % complete as the linked activities are updated but can't seem to get it to work. I have reviewed the forum for similar topics...

Sep 18, 2012

How to highlight activity

Forum Topic

Hello Planners,A small doubt in P6I have 5 activities which i need to get highlight to show to my manager when i creat a pdf file. How can i highlight this activities in Primavera?Thank you in advanceregardsRajesh.

Sep 18, 2012

Pertmaster/risk analysis training in Scotland??

Forum Topic

Hello, Can anyone tell me if there are any pertmaster/risk analysis courses being held in Scotland over the next few months? I'm in Aberdeen but willing to travel.   Thanks!

Sep 18, 2012

Stacked Histogram with Different Calendars in P6

Forum Topic

I have been trying to get an output for the stacked histogram which shows 1 man working 1 shift in a day. The only problem is that I am using both standard 10 hour working days and 3.5 hour night shift. The resources that I have use the correct calen...

Sep 18, 2012

P6 8.2 print preview is taking too much time.

Forum Topic

HiI am experiancing a problem using P6 8.2. when i click print preview, it takes 1-2 minutes and also same thing happens while changing hadder and footer. P6, 6.2 was very smooth.Please help Regards

Sep 18, 2012

Displaying Duration In Phase Title Bar

Forum Topic

On my project I have all the activities organized by phase.  Is there a way to automatically display the total duration of the phase in the title?   For example, if I had a phase 1A, and all the activites in phase 1A would take 30 days to complete, i...

Sep 19, 2012

How do I export my project from P6 to MSP??

Forum Topic

I did try exporting the file from P6 and savin it in.mpp format and then open it MSP, but then not all the linkages, dates match exactly? Can anybody help me on this??

Sep 20, 2012

Change Stacked Histogram Scale - P6

Forum Topic

Have not had too much success of late with any response so fingers crossed for this one.Trying to get a more suitable scale for my Stacked Histogram, the scale goes up to 100 hours whereas the highest value is only about 65 hours. Is there any method...

Sep 20, 2012

Report Editor

Forum Topic

 Hi Experts Can anyone share manuals about the report editor. Since i am struggling to design a new report as required.  Thanks in advanceRams

Sep 20, 2012

Staircase Construction- RCC

Forum Topic

Dear all, When can I start Staircase work 1.Ground floor slab 2 .Columns 3 .beams 4. RCC walls 5. First Floor Slab ------------------------------ 6 .Columns 7.Beams 8. RCC walls 9.Roof Slab From where i can start  RCC staircase construction Thanks

Sep 22, 2012

Cannot update baseline for in progress activities

Forum Topic

Hello PPlanners,I do have a problem with successive baselines: while updating a project, I create a new baseline every month after updating the projectNow some activities are late; say, they will start 2 weeks after the Original Start Date, or finish...

Sep 22, 2012

Forecasting and Trending

Forum Topic

I currently am running projects that are fairly short in duration (3 months).  I progress daily and progress using Physical % Complete since I can measure units completed.  Since the duration of each project is short my CPI seems to be manic.  Up one...

Sep 22, 2012

Time versus Quality

Forum Topic

  Hi All, Does time affects quality or quality affects time? May I ask your opinion. Thanks and regards. Dominador Santos

Sep 23, 2012

Connection Problem

Forum Topic

Can anyone explain this connection problem please? Arrived at work this morning, tried to log on and get this messege?? Everything was fine on Fridat when I left?? Thanks in advance for any advice [[wysiwyg_imageupload:1277:]]

Sep 24, 2012

Variance In Dates between Primavera & PERT master Risk Analysis

Forum Topic

Hi All, I recently loaded my schedule XER in to PRA software to do a risk simulation.But before making any changes i found that the dates are moved to the right side without making any simulation.Anybody faced kind of situation while working in PRA. ...

Sep 24, 2012

Material Resources Assignment in P6

Forum Topic

Dear All, I want to assign material quantities to a constuction plan in P6,Like, Excavation (xx m3)Concreting (xx m3)Structure Erection (xx Tons)etc... etc... Currently I am assigning a Material Resource in Resources. I have made a resource "concreti...

Sep 24, 2012