Staircase Construction- RCC

S
Saju TS 👤 Member for 17 years

Dear all,

When can I start Staircase work

1.Ground floor slab

2 .Columns

3 .beams

4. RCC walls

5. First Floor Slab

------------------------------

6 .Columns

7.Beams

8. RCC walls

9.Roof Slab

From where i can start  RCC staircase construction

Thanks

M
Mike Testro 👤 Member for 20 years 6 months

Hi Saju

You have to have at least two slabs to support the staircase and it can follow the structure upwards.

It depends on the construction method statement because the stairwell may be used for vertical access and hoists.

I would also consider a precast option which can be dropped into place in one day.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts