Level of Effort % Complete

G
Gord Taylor 👤 Member for 13 years 8 months

Hey Guys,

I have a question about Level of Effort. I am using P6 v8.2.

I am trying to get the level of effort to update the % complete as the linked activities are updated but can't seem to get it to work. I have reviewed the forum for similar topics and have tried everything relevant that I found. Setting % complete type, relationship types (SF, SS, FF...).

I built a new simple project with a LOE and with 3 assigned activities. I have tried linking in different orders, setting % complete type to Physical, Units & Duration. No matter what I do the LOE % complete (or activity, units or any other % complete type) will not change as activities are updated.  I also tried to create a start and finish mileston, linking the activities and the LOE back to those. Everything is manpower loaded with costs. What am I missing?

Thanks for feedback.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts