Change Stacked Histogram Scale - P6

Have not had too much success of late with any response so fingers crossed for this one.

Trying to get a more suitable scale for my Stacked Histogram, the scale goes up to 100 hours whereas the highest value is only about 65 hours. Is there any method to force the program to produce a more suitable output.

I have tried Resource Usage Profile Options > Graph > Additional Display Options and Calculate Average, changing divide interval totals by a different factor and set unit of measure but this never has any effect, any ideas why.

Also really looking for an answer to a previous post if anyone is able to help.

Below is Planning Planet link.

http://www.planningplanet.com/forums/primavera-version-pm5-pm6/526629/s…

Thanks for help.

Z
Zoltan Palffy 👤 Member for 16 years 11 months

if you really want to modify the graphics take the information out to excel and play with it all you want.  You ca make any type of graph that you would like and adjust the scaling there but I dont think it can be adjusted in P6

S
Shaikh Shadab 👤 Member for 11 years 2 months

Hiiiii,

I am also facing same problem

please advoice us how to resolve same issue , as ater plotting graph its very difficult to explain the end user. as its not giving any benificial information.

thanks

regards,

Shadab Sk

D
Duncan Pirie 👤 Member for 13 years 8 months

Hi Giles,

 

I wanted to do similiar and was told that it cannot be done, the software dictates.  Not helpful I know, if anyone else knows a work around for this it could be helpful.

 

D

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts