If we can do Time Scale Change - Positive and Negative

Hello Everyone,

Just a doubt about if we can show the time scale to positive and negative.

Like the award )

Project award date would be 0 anything happening after the project award date would be positive dates like (Week) 1 ,2 3.

 

How can we show in the schedule the activities which happens before Project award date as negative like (week) -1 , -2 , -3 etc

Thanks

Jithin

J
Jithin Kambhikanam 👤 Member for 15 years 2 months

Thanks Mike,

Very helpfull and shows us the change in the software.

Haveint used Asta yet. In Middle East the first one / Mostly it is Primavera and the next one is MSP. But its really good to hear all this logic. Probably would study Asta too.

Regards

Jithin

M
Mike Testro 👤 Member for 20 years 5 months

Hi Jithin

In Asta PowerProject I just click on the date that I want to be Week 0 and the + / - numbers just fall into place.

Best regards

Mike Testro

J
Jithin Kambhikanam 👤 Member for 15 years 2 months

Thanks Gary. It Worked out well. I was trying to do many things in timescale and it didnt work. At last as you said i went to the time scale checked marked the Show Original Dates and then in Original start i used the custom date to select the day when the project is awarded.

And in Original Date Interval i selected weeks.

Thanks a lot for helping me out.

Jithin

G
Gary Whitehead 👤 Member for 17 years 2 months

View menu > Timescale

Click "Show Ordinal Dates"

Ordinal Start = Award date

Ordinal Date interval = weeks

Click Apply

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts