Hello Everyone,
Just a doubt about if we can show the time scale to positive and negative.
Like the award )
Project award date would be 0 anything happening after the project award date would be positive dates like (Week) 1 ,2 3.
How can we show in the schedule the activities which happens before Project award date as negative like (week) -1 , -2 , -3 etc
Thanks
Jithin
Thanks Mike. Would be going through it. Would be good to learn more n more.
Jithin
Hi Jithin
You can download a 30 day free trial from www.astadev.com
Best regards
Mike Testro
Thanks Mike,
Very helpfull and shows us the change in the software.
Haveint used Asta yet. In Middle East the first one / Mostly it is Primavera and the next one is MSP. But its really good to hear all this logic. Probably would study Asta too.
Regards
Jithin
Hi Jithin
In Asta PowerProject I just click on the date that I want to be Week 0 and the + / - numbers just fall into place.
Best regards
Mike Testro
Thanks Gary. It Worked out well. I was trying to do many things in timescale and it didnt work. At last as you said i went to the time scale checked marked the Show Original Dates and then in Original start i used the custom date to select the day when the project is awarded.
And in Original Date Interval i selected weeks.
Thanks a lot for helping me out.
Jithin
View menu > Timescale
Click "Show Ordinal Dates"
Ordinal Start = Award date
Ordinal Date interval = weeks
Click Apply
Couldnt get to know how to do that. Could you please explain.
Use the Ordinal Dates....
Primavera 6
What software are you using?