Finishes vs External Envelope
Forum Sponsor
Top Posters
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
Hi Edniel
It depends on the specification but usually you need weathertight conditions for trades that may be damaged by water intrusion - such as listed by Jacob.
So it is not just the facade but the roof as well.
Once you have a clear working platform and a secure deck above - usually 2 floors - then items such as:
1. Internal masonry - may have to wait a bit until the facade is in place.
2. MEP Ducts - pipes - electric containment but NOT cables.
3. MEP in risers must have a secure walls and top cover.
Best regards
Mike Testro
Dear All,
Thanks Jacob.
Could other PPers give me their contributions on the subject regardless in which country is the location of the project.
Thanks,
Edniel
for philippines which are typhoon affected countries
All dry items like gypsum boarding works (drywall and ceiling), carpentries/wooden items, also paints