Hi Edniel



It depends on the specification but usually you need weathertight conditions for trades that may be damaged by water intrusion - such as listed by Jacob.



So it is not just the facade but the roof as well.



Once you have a clear working platform and a secure deck above - usually 2 floors - then items such as:



1. Internal masonry - may have to wait a bit until the facade is in place.

2. MEP Ducts - pipes - electric containment but NOT cables.

3. MEP in risers must have a secure walls and top cover.



Best regards



Mike Testro

E
Edniel Recamadas 👤 Member for 17 years 2 months

Dear All,



Thanks Jacob.



Could other PPers give me their contributions on the subject regardless in which country is the location of the project.



Thanks,



Edniel

2
27141 👤 Member for 17 years 7 months

for philippines which are typhoon affected countries



All dry items like gypsum boarding works (drywall and ceiling), carpentries/wooden items, also paints

Forum Sponsor

Top Posters

James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts