RESOURCE UNIT changed

J
JV Amande 👤 Member for 18 years 3 months
V
Vladimir Liberzon 👤 Member for 25 years 4 months

I don’t think that you will find a solution.

In Spider Project there is special material property - discrete consumption. If it is not selected then materials are consumed in the proportion of the work done.

I do not remember this feature in P3.

Best Regards,

Vladimir

J
JV Amande 👤 Member for 18 years 3 months



Shahul;



Thanks for your idea, i am also aware of that. But i want to retain it to a whole number,



say 1 day of task... then i input 1 unit of

resource.



After i run/schedule.. i recheck my resource/s and it turns out into 0.0~ something. It’s no whole number of unit.



I encounter this just lately.



Isn’t it the 1-unit of resource that i input should remain as 1-unit? How come it will become.. 0.0~ or not a whole number.





Hi Mike;



I’m only using P3.

S
Shah. HB 👤 Member for 17 years 6 months

Hi JV

In P3 once you assign budgeted quantity ,it gets divided by activity original duration to get units per day ,the decimals you are talking about is unit per day I trust .




Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts