I dont think that you will find a solution.
In Spider Project there is special material property - discrete consumption. If it is not selected then materials are consumed in the proportion of the work done.
I do not remember this feature in P3.
Best Regards,
Vladimir
Shahul;
Thanks for your idea, i am also aware of that. But i want to retain it to a whole number,
say 1 day of task... then i input 1 unit of
resource.
After i run/schedule.. i recheck my resource/s and it turns out into 0.0~ something. Its no whole number of unit.
I encounter this just lately.
Isnt it the 1-unit of resource that i input should remain as 1-unit? How come it will become.. 0.0~ or not a whole number.
Hi Mike;
Im only using P3.
Hi JV
In P3 once you assign budgeted quantity ,it gets divided by activity original duration to get units per day ,the decimals you are talking about is unit per day I trust .
Hi JV
What software are you using?
Best regards
Mike Testro