RESOURCE UNIT changed

J
JV Amande 👤 Member for 18 years 3 months
V
Vladimir Liberzon 👤 Member for 25 years 4 months

I don’t think that you will find a solution.

In Spider Project there is special material property - discrete consumption. If it is not selected then materials are consumed in the proportion of the work done.

I do not remember this feature in P3.

Best Regards,

Vladimir

J
JV Amande 👤 Member for 18 years 3 months



Shahul;



Thanks for your idea, i am also aware of that. But i want to retain it to a whole number,



say 1 day of task... then i input 1 unit of

resource.



After i run/schedule.. i recheck my resource/s and it turns out into 0.0~ something. It’s no whole number of unit.



I encounter this just lately.



Isn’t it the 1-unit of resource that i input should remain as 1-unit? How come it will become.. 0.0~ or not a whole number.





Hi Mike;



I’m only using P3.

S
Shah. HB 👤 Member for 17 years 7 months

Hi JV

In P3 once you assign budgeted quantity ,it gets divided by activity original duration to get units per day ,the decimals you are talking about is unit per day I trust .




Forum Sponsor

Top Posters

James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts