Resource Allocation issue

Hi, I am using V23.12.

I have a fairly small schedule which is fully resource loaded. All dates etc. are correct folowing update.

However, on one activiy in particular, the resource loading has been spread way beond the activity completion date.

Activity completion date is 23 Sept and the resource loading goes on into November. Curve is linear and late dates are only 2 days beyond finish dates.

Anybody any ideas how to correct this?

Thanks

Z
Zoltan Palffy 👤 Member for 16 years 11 months

it should go until September becasuse 23 Sept is you completion date

are you looking at remaing early histogram ?

K
Kevin John McGovern 👤 Member for 18 years 11 months

Apologies for all the duplicate messages. No idea how that happened.

Anyway, issu is now solved :)

K
Kevin John McGovern 👤 Member for 18 years 11 months

Apologies for all the duplicate messages. No idea how that happened.

Anyway, issu is now solved :)

K
Kevin John McGovern 👤 Member for 18 years 11 months

Apologies for all the duplicate messages. No idea how that happened.

Anyway, issu is now solved :)

A
Alex Lyaschenko 👤 Member for 14 years 10 months

If it is ok for you. I can run your schedule via external schedule analysis tool to identify the problem. 

 

Alex Lyaschenko

K
Kevin John McGovern 👤 Member for 18 years 11 months

Further udate on the above.

My data date is 04 Aug and I have activities already completed in July. However, the resource Assignments spreadsheet shows the planned resource going on until September.

This has me completely stumped 

K
Kevin John McGovern 👤 Member for 18 years 11 months

Further udate on the above.

My data date is 04 Aug and I have activities already completed in July. However, the resource Assignments spreadsheet shows the planned resource going on until September.

This has me completely stumped 

K
Kevin John McGovern 👤 Member for 18 years 11 months

Further udate on the above.

My data date is 04 Aug and I have activities already completed in July. However, the resource Assignments spreadsheet shows the planned resource going on until September.

This has me completely stumped 

K
Kevin John McGovern 👤 Member for 18 years 11 months

Further udate on the above.

My data date is 04 Aug and I have activities already completed in July. However, the resource Assignments spreadsheet shows the resource goin on until September.

This has me completely stumped 

K
Kevin John McGovern 👤 Member for 18 years 11 months

Further udate on the above.

My data date is 04 Aug and I have activities already completed in July. However, the resource Assignments spreadsheet shows the resource goin on until September.

This has me completely stumped 

Forum Sponsor

Top Posters

christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts