Hi, I am using V23.12.
I have a fairly small schedule which is fully resource loaded. All dates etc. are correct folowing update.
However, on one activiy in particular, the resource loading has been spread way beond the activity completion date.
Activity completion date is 23 Sept and the resource loading goes on into November. Curve is linear and late dates are only 2 days beyond finish dates.
Anybody any ideas how to correct this?
Thanks
it should go until September becasuse 23 Sept is you completion date
are you looking at remaing early histogram ?
If it's okay for you, can you share with us the cause of the issue?
If it's okay for you, can you share with us the cause of the issue?
Apologies for all the duplicate messages. No idea how that happened.
Anyway, issu is now solved :)
Apologies for all the duplicate messages. No idea how that happened.
Anyway, issu is now solved :)
Apologies for all the duplicate messages. No idea how that happened.
Anyway, issu is now solved :)
If it is ok for you. I can run your schedule via external schedule analysis tool to identify the problem.
Alex Lyaschenko
Further udate on the above.
My data date is 04 Aug and I have activities already completed in July. However, the resource Assignments spreadsheet shows the planned resource going on until September.
This has me completely stumped
Further udate on the above.
My data date is 04 Aug and I have activities already completed in July. However, the resource Assignments spreadsheet shows the planned resource going on until September.
This has me completely stumped
Further udate on the above.
My data date is 04 Aug and I have activities already completed in July. However, the resource Assignments spreadsheet shows the planned resource going on until September.
This has me completely stumped
Further udate on the above.
My data date is 04 Aug and I have activities already completed in July. However, the resource Assignments spreadsheet shows the resource goin on until September.
This has me completely stumped
Further udate on the above.
My data date is 04 Aug and I have activities already completed in July. However, the resource Assignments spreadsheet shows the resource goin on until September.
This has me completely stumped