Hi Guys,
Do any of you have a report that identifies activities that have external relationships? I can't find the correct way to generate a report.
Thanks,
Rod
Hi Guys,
Do any of you have a report that identifies activities that have external relationships? I can't find the correct way to generate a report.
Thanks,
Rod
activites that have exteranl relationships will have an asterick in the start date column
Option 1 go to tools schedule
select options
then select ignore relationships to and from other projects
option #2
filter for all activities
right click columns
expand the dates availability on the left and choose
External Early Start and also choose External Early Finish
now in the External Early Start column Blank out the dated
now do a fill down a
Now do the same thing for the External Early Finish Column
Option #3
go to tools
global change
New (on the right)
Where (leave this line blank)
then
External Early Start = (leave the rest of the line blank)
and
External Early Finish = (leave the rest of the line blank)
then on the right select change
then commit changes
what ever option that you choose make sure to run the schedule calculations after you run your option
Thanks Santosh & Rodel, both suggestions very worthwhile.
Rod
Rodney, take a look here: Listing P6 Inter-Project Relationships | Australasian Project Planning (austprojplan.com.au)
The easiest way is to export the Activity Relationship to Excel. Make sure to include the 'Predecessor Project' and 'Successor Project' columns. You can then filter from these two columns for the external project links to your Project.