How to find External Relationships

Hi Guys,

 

Do any of you have a report that identifies activities that have external relationships? I can't find the correct way to generate a report.

 

Thanks,

 

Rod

Z
Zoltan Palffy 👤 Member for 16 years 11 months

activites that have exteranl relationships will have an asterick in the start date column

Option 1  go to tools schedule 

select options

then select ignore relationships to and from other projects

option #2

filter for all activities

right click columns 

expand the dates availability on the left and choose

External Early Start and also choose External Early Finish

now in the External Early Start column Blank out the dated 

now do a fill down a

Now do the same thing for the External Early Finish Column

Option #3

go to tools

global change

New (on the right)

Where  (leave this line blank)

then

External Early Start = (leave the rest of the line blank)

and

External Early Finish = (leave the rest of the line blank)

then on the right select change

then commit changes

 

what ever option that you choose make sure to run the schedule calculations after you run your option

R
Rodel Marasigan 👤 Member for 19 years 7 months

The easiest way is to export the Activity Relationship to Excel. Make sure to include the 'Predecessor Project' and 'Successor Project' columns. You can then filter from these two columns for the external project links to your Project.

Forum Sponsor

Top Posters

sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts