Part days of float

P
Paul Harris 👤 Member for 25 years 2 months

There are many reasons why this may happen, but displaying the times with the date is the first step to resolving what is happening.



Then as Brian has indicated check that you default start and finish times are aligned with your calendars.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au


B
Brian Ultican 👤 Member for 19 years

Go into Tools | Options | View and pick a date format that shows the time.



It is possible that the Finish date of the task in question as a time on it that is not the same as the default end time for the calendar.

A
Alexandre Faulx-Briole 👤 Member for 23 years 5 months

Stuart,

1. did you put a date constraint on one task?

2. did you change something in the calendars or calendar options?

Regards,

Alexandre

Forum Sponsor

Top Posters

Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts