Part days of float

P
Paul Harris 👤 Member for 25 years 3 months

There are many reasons why this may happen, but displaying the times with the date is the first step to resolving what is happening.



Then as Brian has indicated check that you default start and finish times are aligned with your calendars.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au


B
Brian Ultican 👤 Member for 19 years 1 month

Go into Tools | Options | View and pick a date format that shows the time.



It is possible that the Finish date of the task in question as a time on it that is not the same as the default end time for the calendar.

A
Alexandre Faulx-Briole 👤 Member for 23 years 6 months

Stuart,

1. did you put a date constraint on one task?

2. did you change something in the calendars or calendar options?

Regards,

Alexandre

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts