No Subject Specified

Member for

19 years 10 months

Hi All



The original post was:



There are four different techniques to do the delay analysis



1-As-Planned Vs As-Built

Best used when Sub-Contract work is compressed between other trades.

2-Impacted As-Planned

Used for on-going work

3-Collapsed As-Built

Completely unreliable - don’t even go there.

4-Time Impact Analysis

Best for forensic analysis but must have accurate As Buit data to be effective.



I hope this is clear



Best regards



Mike Testro

Member for

18 years 6 months

Page 101 shows when it is best to use each method.

Member for

18 years 6 months

khawaja uddin,



Try reading this, you might find it useful.



AACE International Recommended Practice No. 29R-03

FORENSIC SCHEDULE ANALYSIS