Forensic Claims Analysis Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Fri, 2008-07-18 10:22 Permalink RE: No Subject Specified Hi All The original post was: There are four different techniques to do the delay analysis 1-As-Planned Vs As-Built Best used when Sub-Contract work is compressed between other trades. 2-Impacted As-Planned Used for on-going work 3-Collapsed As-Built Completely unreliable - dont even go there. 4-Time Impact Analysis Best for forensic analysis but must have accurate As Buit data to be effective. I hope this is clear Best regards Mike Testro Member for 18 years 6 months Member for 18 years 6 months Submitted by Oliver Melling on Fri, 2008-07-18 09:37 Permalink RE: No Subject Specified Page 101 shows when it is best to use each method. Member for 18 years 6 months Member for 18 years 6 months Submitted by Oliver Melling on Fri, 2008-07-18 09:03 Permalink RE: No Subject Specified khawaja uddin, Try reading this, you might find it useful. AACE International Recommended Practice No. 29R-03 FORENSIC SCHEDULE ANALYSIS Log in or register to post comments
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Fri, 2008-07-18 10:22 Permalink RE: No Subject Specified Hi All The original post was: There are four different techniques to do the delay analysis 1-As-Planned Vs As-Built Best used when Sub-Contract work is compressed between other trades. 2-Impacted As-Planned Used for on-going work 3-Collapsed As-Built Completely unreliable - dont even go there. 4-Time Impact Analysis Best for forensic analysis but must have accurate As Buit data to be effective. I hope this is clear Best regards Mike Testro
Member for 18 years 6 months Member for 18 years 6 months Submitted by Oliver Melling on Fri, 2008-07-18 09:37 Permalink RE: No Subject Specified Page 101 shows when it is best to use each method.
Member for 18 years 6 months Member for 18 years 6 months Submitted by Oliver Melling on Fri, 2008-07-18 09:03 Permalink RE: No Subject Specified khawaja uddin, Try reading this, you might find it useful. AACE International Recommended Practice No. 29R-03 FORENSIC SCHEDULE ANALYSIS
Member for
19 years 10 monthsRE: No Subject Specified
Hi All
The original post was:
There are four different techniques to do the delay analysis
1-As-Planned Vs As-Built
Best used when Sub-Contract work is compressed between other trades.
2-Impacted As-Planned
Used for on-going work
3-Collapsed As-Built
Completely unreliable - dont even go there.
4-Time Impact Analysis
Best for forensic analysis but must have accurate As Buit data to be effective.
I hope this is clear
Best regards
Mike Testro
Member for
18 years 6 monthsRE: No Subject Specified
Page 101 shows when it is best to use each method.
Member for
18 years 6 monthsRE: No Subject Specified
khawaja uddin,
Try reading this, you might find it useful.
AACE International Recommended Practice No. 29R-03
FORENSIC SCHEDULE ANALYSIS