Mike Testro 👤 Member for 20 years 5 months

Hi All



The original post was:



There are four different techniques to do the delay analysis



1-As-Planned Vs As-Built

Best used when Sub-Contract work is compressed between other trades.

2-Impacted As-Planned

Used for on-going work

3-Collapsed As-Built

Completely unreliable - don’t even go there.

4-Time Impact Analysis

Best for forensic analysis but must have accurate As Buit data to be effective.



I hope this is clear



Best regards



Mike Testro

O
Oliver Melling 👤 Member for 19 years 1 month

khawaja uddin,



Try reading this, you might find it useful.



AACE International Recommended Practice No. 29R-03

FORENSIC SCHEDULE ANALYSIS

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts