Hi All
The original post was:
There are four different techniques to do the delay analysis
1-As-Planned Vs As-Built
Best used when Sub-Contract work is compressed between other trades.
2-Impacted As-Planned
Used for on-going work
3-Collapsed As-Built
Completely unreliable - dont even go there.
4-Time Impact Analysis
Best for forensic analysis but must have accurate As Buit data to be effective.
I hope this is clear
Best regards
Mike Testro
Page 101 shows when it is best to use each method.
khawaja uddin,
Try reading this, you might find it useful.
AACE International Recommended Practice No. 29R-03
FORENSIC SCHEDULE ANALYSIS