Update Daily progress from excel into planning tool

G
G T 👤 Member for 15 years 4 months

Dear Forum

Could yo kindly help me please with my question that i am struggling much:



There is task (actually lots of tasks, but for simplicity i will consider 1 task) that started at some time in the past and gradually was progressing on a daily basis.

So there are daily progress report excel files listing each day how many % was completed.

How can it be loaded automatically into MS Project / Primavera (or what tool would you recommend ?) showing progress of each day / cumulative daily progress to have a curve - visually to see how slow or fast it is progressing and to compare with baseline curve / graph...

 

Thank you so much.

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Patrick, I don't agree with your statement that "For 99% of the world's projects a schedule update every 2 weeks and a full project update every month is adequate".

In our practice 99% of construction projects are updated at least once in a week, and daily in STO projects.

Project team meetings with performance analysis are usually held weekly and these meetings require updated information on project status and trends for informed decision making. Projects in trouble are updated daily.

In STO time is very expensive and uncertainties can be high. So project is updated each shift.

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Patrick, I don't agree with your statement that "For 99% of the world's projects a schedule update every 2 weeks and a full project update every month is adequate".

In our practice 99% of construction projects are updated at least once in a week, and daily in STO projects.

Project team meetings with performance analysis are usually held weekly and these meetings require updated information on project status and trends for informed decision making. Projects in trouble are updated daily.

In STO time is very expensive and uncertainties can be high. So project is updated each shift.

Profile picture for Patrick Weaver
Patrick Weaver 👤 Member for 25 years 4 months

If you want people to take note of the shedule and actually try to work to the schedule changing it every day is counterproductive if your project is running for more then a couple of weeks.  What's needed is action to get back onto schedule from the project team: https://mosaicprojects.com.au/PMKI-SCH-014.php#Process6 

For 99% of the world's projects a schedule update every 2 weeks and a full project update every month is adequate to understand where the project is and overall trends - the rest of the time the focus should be on working the schedule. 

V
Vladimir Liberzon 👤 Member for 25 years 4 months

It is possible in Spider Project.

But we prefer to collect not percent complete but volumes of work in physical units (m3, m, t, etc.) that were done at any reporting period. Volumes are measurable, percents are subjective.

Actual data can be imported from Excel but it is easier to fill table form created by Spider Project.

D
david kelly 👤 Member for 10 years 3 months

At the moment for each in progress activity, the known historic datapoints are date started, current data date and percent complete. The date started and current percent complete can be imported from Excel.

In order to accurately draw an "s" curve, you need to preserve the percent complete for each data date. Thic can be done by creating what P6 calls a Financial calendar, and then running the process called Store Period Performance .

BUT the smallest interval in a Financial Calendar is one week. Daily progress figures are not supported.

 

D
david kelly 👤 Member for 10 years 3 months

At the moment for each in progress activity, the known historic datapoints are date started, current data date and percent complete. The date started and current percent complete can be imported from Excel.

In order to accurately draw an "s" curve, you need to preserve the percent complete for each data date. Thic can be done by creating what P6 calls a Financial calendar, and then running the process called Store Period Performance .

BUT the smallest interval in a Financial Calendar is one week. Daily progress figures are not supported.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts