Afternoon,
OK, so hyperhetical question....let say someone has 'mis-placed' the original P6 schedule....Is there any way of converting a Reflection schedule in to a 'master' schedule without merging it back to its original?
Thanks,
Phil.
Afternoon,
OK, so hyperhetical question....let say someone has 'mis-placed' the original P6 schedule....Is there any way of converting a Reflection schedule in to a 'master' schedule without merging it back to its original?
Thanks,
Phil.
just create a dummy project
Use SQL server management studio and overwrite the source project ID with a null.