calculation of cost for non labour resources assigned to all the project.

 

 

 

Please some one can explain me How to calculate cost for non labour resources assigned to all the project with a given price/day.

cost should be calculated even for the non worked day(week end).

A
amar iadaden 👤 Member for 7 years 11 months

Thank you very much David.we also use level of effort for all equipment used along the project i think.

D
david kelly 👤 Member for 10 years 3 months

If your activities are on a five-day week, BUT your non-labour resources can only be hired by a seven-day week, then the simplest ways to incorporate the costs is to create a daily cost for the resource which is 7/5ths of the weekly cost.

BUT

If you then decide to work at the weekend there is a problem

My choice would be to create WBS Summary activity or activities (whose duration is automatically calculated as the duration of the WBS) with Fixed Units per Time period as the duration type, a seven-day calendar, and all the non-labour resources are attached to those activities. This will do the correct calculations for non-labour costs.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts